TCN provides detailed reasons for the nationwide poor electricity supply

Rate this item
(0 votes)

PRESS RELEASE

The Transmission Company of Nigeria wishes to notify consumers of electricity that the current load shedding being experienced nationwide is as a result of very low power generation by the Generation Companies (GENCOs) for TCN to wheel through the transmission grid to distribution companies nationwide.

The media has been awash with reports that TCN has reduced the load allocation to distribution companies. That information is incorrect. The correct position is that TCN can only transmit the quantum of power generated by GenCos through the national grid to distribution load centres nationwide.

For clarity, TCN does not generate electricity and therefore can only transport cumulative generation from all the generation companies nationwide to distribution load centres. The distribution companies are responsible for end-users consumption. TCN allocates power to distribution companies based on approved percentage (formula approved by NERC), of the total generation available per hour or on day-ahead nomination.

Presently,  the cumulative generation nationwide is low and generation companies have attributed this to several factors including poor gas supply, fault in generating units of generating companies, scheduled and unscheduled maintenance, all of which have caused most power generating companies to limit their generation, and sometimes not  generate at all.

A summary of the power generating profiles in the last two months, for instance, clearly shows that fourteen (14) gas powered generating stations were either not generating at all or had limited generation at various times within the period, further depleting the quantum of power generation available for transmission into the grid on a daily basis. Power generating stations in this category include; Omotosho units 5 & 6, Olorunsogo units 3, 4 & 6, Omoku units 3 & 6, Omotosho NIPP units 3 & 4, Delta units 15, 17, and 18, Afam VI units 11 & 12, Olorunsogo NIPP unit 3, Ihovbor NIPP unit 2, Sapele Steam unit 3, Sapele NIPP unit 1, Odukpani NIPP units 1 & 3, and Okpai units 11, 12 & 18.

Also, within the same period, Jebba Hydro and Shiroro Power Generating Stations were either out or had limited generation, causing additional loss of 232MW from the grid, while other power generating plants such as  Omotosho units 3&4, Olorunsogo units 1, Delta units 10 &20, Afam VI  unit 13, Ihovbor NIPP units 4, Geregu NIPP units 22&23 and Odukpani NIPP units 2, 4 & 5, have also been out either on fault or for scheduled maintenance, causing a further loss of about 3,180MW from the grid.

A combination of the above scenarios have persisted and the total effect on the grid is persistent low generation, which TCN Operators have had to strive to dispatch in a way that will not jeopardize the stability of the grid.

More recently, from the 1st to 4th of March, 2022, there was generation shortfall due to water management in Shiroro and Jebba hydro with the loss of 307MW and 125MW respectively from both stations. Within the same period, there were fault and technical problems in Egbin, causing 514MW shortfall and in Geregu causing 230MW shortfall, while reported fault at Alaoji NIPP reduced generation from the substation by 263MW.

Gas constraint alone in Olorunsogo gas generating plant reduced generation from the station by 104MW, in the same vein,  Omotosho gas lost 102MW and Sapele NIPP lost 263MW. In Omotosho NIPP, there was generation shortfall of 233MW and in Omoku a shortfall of 112MW. Two units in Okpai have limited generation due to technical problems causing a 204MW drop in generation and in Afam VI 511MW drop in generation.

Gas constraint and fault in Olorunsogo NIPP reduced generation by 240MW, Geregu NIPP by 435MW, and Ihovbor by 142MW.  Also, due to gas pipeline pigging, Odukpani NIPP was SHUT DOWN which caused a reduction of generation by 575MW.

TCN further reiterates that a combination of issues ranging from gas constraints, fault, and technical problems within generating plants caused persistent low generation and consequently low load allocation to Distribution Companies nationwide. This is based on the fact that TCN can only transmit what is being generated by GenCos and presently they are all generating below capacity.

It is important to note that except cumulative power generation increases considerably for TCN to transmit to distribution companies nationwide, TCN will be left with no choice than to continue to load shed. We will however continue to work hard to ensure the efficient allocation of the total load generated by power generating stations into the grid, bearing in mind the need to ensure that the national grid is stable in spite of the challenges posed by insufficient load on the transmission grid.

Signed

Ndidi Mbah

GM, Public Affairs

8/3/22

May 10, 2025

Marketers import N2.4tn petrol as competition with Dangote Refinery intensifies

Tensions have escalated between major oil marketers and the Dangote petroleum refinery as they compete…
May 10, 2025

Multiple political parties hinder governance, one-party system could work - Ganduje

Abdullahi Ganduje, national chairman of the All Progressives Congress (APC), suggested that a one-party system…
May 10, 2025

The No. 1 lesson I learnt about relationship building, from a human connection specialist

Developing healthy, lifelong connections is something that Mark Groves knows all about: He equips individuals…
May 10, 2025

Town residents involutarily get high after Police burn 20 tons of confiscated cannabis

The 25,000 residents of Lice, a town in Turkey’s Diyarbakır province, involuntarily got high after…
May 10, 2025

Gunmen kill 30 travellers, burn 20 vehicles in Imo, Amnesty says

Gunmen shot dead at least 30 travellers in an attack in Nigeria's southeastern Imo state,…
May 10, 2025

Here’s the latest as Israel-Hamas war enters Day 582

Israel won't be involved in new Gaza aid plan, only in security, US envoy says…
May 07, 2025

The first driverless ‘trailers’ have started running regular longhaul routes

Driverless trucks are officially running their first regular long-haul routes, making roundtrips between Dallas and…
January 08, 2025

NFF appoints new Super Eagles head coach

The Nigeria Football Federation (NFF) has appointed Éric Sékou Chelle as the new Head Coach…

NEWSSCROLL TEAM: 'Sina Kawonise: Publisher/Editor-in-Chief; Afolabi Ajibola: IT Manager;
Contact Us: [email protected] Tel/WhatsApp: +234 811 395 4049

Copyright © 2015 - 2025 NewsScroll. All rights reserved.